CONSTRUCTION MANAGEMENT Fixtures and fittings and external works

PROJECT TITLE

Overseeing and directing the development of 474 civil engineering component infrastructures in the provinces of Bas-Uélé, Tshopo, and Mongala (Lot 3 / 226 infrastructures) and Kasaï, Tshuapa, and Sankuru (Lot 2 / 248 infrastructures)

More

Characteristics
Single-story buildings: 196 Schools; 140 Health Centers and 29 administrative buildings. Cost of the works: 92,015,284.13 USD; Land area: approx. 2500 m²/site; Developed floor area: 109,500 m².

Missions:
DET, OPC, and AOR missions

Project

Client PNUD
Country RDC
Donor Government of Congo
Overall cost of works ninety-two million fifteen thousand two hundred eighty-four ( USD)

EXPERTISE

Sector GESTION DES CONSTRUCTIONS--Fixtures and fittings and external works
Project duration 7 Month