Characteristics
Construction of 5 schools (CES of CAP ESTERIAS built on 2 ha, Alibandeng School Complex (Kiliba) built on 2.6 ha, Ondogo Primary School built on 0.40 ha, CES of Avorbam built on 0.83 ha, CES of Angondjé built on 0.52 ha) with R+1 buildings.
Construction cost: 6 billion FCFA; Land area: 6.2 ha; Developed floor area: 11,000 m².

Missions
Studies (Diagnostic, Preliminary Design, Detailed Design–Execution Documents, and Tender Assistance) for technological lots (electrical systems – high and low current, HVAC, sanitary plumbing, fire protection, sanitation and external works/urban utilities).

Project

Client Egis
Country Gabon
Donor AFD
Overall cost of works six billion ( FCFA)