CONSTRUCTION MANAGEMENT Drinking water supply

PROJECT TITLE

Technical assessment mission of the condition of an irrigation system in the Gatete area in the commune of BUSONI, KIRUNDO province

More

Characteristics
Reservoir in BA of 6000m3; supply network of 2.5km, distribution network of 9km; Irrigated area estimated at 478 hectares, electrical supply provided by a 280KWc solar power plant and a 400KVA generator.

Missions:
Technical assessment of the current situation, Analysis of gaps and needs and Identification of priority action tracks for the continuation of the project.

Project

Client PNUD
Country Burundi
Donor Government

EXPERTISE

Sector GESTION DES CONSTRUCTIONS--Drinking water supply
Project duration 1 Month